MHHS hits M14 on time: what energy suppliers face between now and the end of migration

Electricity pylon and power lines against an evening sky

On 28 October 2026 the Market wide Half Hourly Settlement programme cleared one of its biggest hurdles. Elexon confirmed that every company planning to take part in half hourly settlement had qualified, meeting the deadline for Milestone 14 on the planned date. Around 75 per cent of meters had already migrated to the new arrangements by then.

For a programme that has been replanned more than once, hitting a major milestone on time matters. It also changes the job in front of suppliers. Here is what M14 means and what comes next. If you need the basics first, start with our guide to what MHHS is.

What M14 changed

Qualification is the assurance that a market participant has the systems, processes and controls to operate under the new settlement arrangements. With M14 passed, every participant is set up to work in the new world.

That also closes a door. Between the start of migration in October 2025 and the qualification deadline, reverse migration allowed a migrated meter to move back into the old arrangements where the gaining supplier was not yet qualified. That interim process was only ever needed until M14. From here, the direction of travel is one way.

Power lines crossing a yellow field under a blue sky

The road to May 2027

Two dates now matter most.

  • M15, 7 May 2027: the end of migration. Every MPAN should be in the new arrangements by this date.
  • M16, 2 July 2027: cutover to the new, faster settlement timetable.

Ofgem has put real weight behind M15. Under BSC modification P487, approved on 30 April 2026, a supplier that has not finished migrating its MPANs by 7 May 2027 will be restricted from registering new customers until its migration is complete. It can keep serving existing customers, and MPANs can be exempted where the delay is genuinely outside the supplier’s control. But for any supplier still growing, losing the ability to take on new customers is a serious commercial risk.

Settlement timing is already moving too. The programme has approved the first step in shortening final reconciliation from 14 months to seven, on the way to the faster timetable planned under M16. Elexon has also said that from October 2026 it will publish aggregated data from the meters that have moved across.

What suppliers should be doing now

Hitting M14 proves the systems work. The last quarter of migration tests whether the operation around them can keep up. The final stretch of any migration tends to be the hardest, because what is left is what did not go smoothly the first time. A few things deserve attention now.

Know your M15 exposure. Map every MPAN still to migrate against your plan and flag anything at risk of slipping past 7 May 2027. Under P487 that is a commercial question, not just an operational one.

Clear exceptions quickly. Rejected flows, mismatched meter details and registration errors pile up fast when volumes are high, and every one sitting in a queue is a settlement risk.

Watch the data, not just the dashboard. Shorter reconciliation windows mean less time to correct bad reads and estimates before they become settled cost.

Keep customers informed. Billing changes and new data can trigger contacts and complaints, so make sure frontline teams know what is changing and when.

Where OptiFlow fits

OptiFlow Utilities sits on top of the systems you already run and takes on the repetitive work that slows a migration down: working through erroneous data flows, handling MHHS exceptions and keeping customer contact under control. It does not replace your billing or settlement platform. For a fuller picture of the flows involved, our guide to UK energy data flows is a good place to start.

If the last stretch of migration is putting pressure on your team, get in touch and we can talk it through.

Frequently asked questions

Was MHHS M14 met?

Yes. Elexon confirmed on 28 October 2026 that all companies planning to take part in half hourly settlement had qualified, meeting the M14 deadline on time.

When does MHHS migration end?

Migration is due to finish at M15 on 7 May 2027, with cutover to the new settlement timetable at M16 on 2 July 2027.

What happens if a supplier misses M15?

Under P487, a supplier that has not completed migration by M15 will be restricted from registering new customers until its migration is complete. Existing customers are not affected, and exemptions can be granted where the delay is outside the supplier’s control.

Sources: Elexon, Ofgem P487 decision, Elexon on MHHS and the BSC, MHHS Programme

Related reading

Need a hand? Ask me anything about OptiFlow.
O

Otis

AI assistant · Online now
Powered by OptiFlow
90Day Guarantee

The 90 Day Money Back Guarantee

If Otis does not lift your conversion in 90 days, you get your money back.

Measured against your website conversion rate in the 30 days before Otis goes live. If it is not higher after 90 days, we refund the Otis fees for that period. Applies to the initial term and the metric agreed at sign up.

Take the free 60 second audit